Castle Towers

Project Description

Transform an existing car park, retail space and major retail into a brand new food court, seating, mixed retail, 2 mini major retail spaces and metro entrance whilst the shopping centre continued to trade uninterrupted.

Level 1 works included 4 new switch rooms (called node rooms for this project) consisting of metered and unmetered distribution boards getting fed by 2 different main switch rooms. Copper and fiber backbones and 2 x Cat6 horizontal cabling to each tenancy.

Node room 1 consists of:

  • A metered house board to feed general light and power in the common and BOH areas surrounding the node. This boards source of supply was 191m through live car park
  • Dali Rapix control gear for the lighting circuits.
  • Large 400A unmetered tenancy distribution board with space for 4 CT metering chambers also feeding a meter panel board with provision for 13 whole current meters with service fuses and main circuit breakers encompassed within the 1 board
  • 4 CT metering panels
  • 42RUCommunications rack with dedicated power supply
  • 27way telephone frame with 200 incoming copper pairs

Node room 2 consists of:

  • A metered house board to feed general light and power in the common and BOH areas surrounding the node. This boards source of supply was 140m through live car park and across a live road on new fire rated cable tray.
  • Dali Rapix control gear for the lighting circuits.
  • 630A meter panel board with provision for 24 whole current meters with service fuses and main circuit breakers encompassed within the 1 board. This board came in 2 parts and needed to be built together by the onsite team
  • Large 400A unmetered tenancy distribution board with space for 4 CT metering chambers
  • 4 CT metering panels
  • 42RUCommunications rack with dedicated power supply
  • 27way telephone frame with 200 incoming copper pairs
  • Cat6A cabling run throughout the public area for public access WiFi
  • Deletion of board under stairs
  • Deletion and relocation of DB3/1

Project Accolade

  • The accomplishment to finish on time and within budget even though the project was delayed for almost 3 months at the beginning. Managing multiple shift start and finish times throughout the 24hr period and having multiple subcontractors working throughout the length of the job with no LTI’s. Initially the builder was sceptical of our ability to complete the job, we turned them into believers and now key personnel now request us to work for them